PennDOT Continues Local Roadwork

PennDOT workers stand guard at the entrance to the Citizens Bridge in Kittanning as it closed on Wednesday night at 7PM. The southern side of the bridge was opened to outbound traffic only beginning at 3AM on Thursday morning.

 

Kittanning Truss Project

The Citizens Bridge in downtown Kittanning switched to the phase two configuration beginning Thursday, August 28 at approximately 3AM. The bridge was closed to traffic during this work that was performed overnight. Flaggers were placed at both ends of the bridge to make sure motorists did not travel into the work zone. With the southern side of the bridge painted, canvas tarps and equipment was moved on Wednesday evening to the northern side of the bridge to begin phase two. The second phase is nearly six weeks behind the original estimate due to damp weather throughout the summer.

No work is planned for Saturday, Sunday, or Monday during the holiday weekend.

The detour for phase two remains the same as phase one. Traffic is permitted to cross the bridge from Kittanning to West Kittanning.

Theater Road

The contractor will be placing subbase and installing drainage on the final roadway this week and paving the last section beginning in September.

Fifth Avenue Ford City

The curb ramps are completed. The contractor will be working on roadway patches and notching out the side roads this week in preparation to finish the paving. Lines are painted on each layer of paving for safety. The final line painting will be performed once the final layer of asphalt is placed. The project is expected to be completed after the Labor Day Holiday.

Garrets Run Bridge

The project is on schedule. The contractor is forming the abutment caps and plans to place the beams on September 8.

 